First off I would like to say how addicting this site is and that the amount of knowledge I've gained is amazing. I have been lurking around for several months but I'm finally about to begin my project. It will be a 50'x50'x14' shop to house my restoration projects.
My question is this, there is an existing 20'x24' 4-inch thick slab in the center of where my new shop is going. Can I level up the remaining ground to the existing slab height and then pour over that? The plans call for a 4" thick slab with a 12"x12" footing around the perimeter of the building.
Any thoughts, suggestions, or ideas would be greatly appreciated.
Thanks,
Matt
My question is this, there is an existing 20'x24' 4-inch thick slab in the center of where my new shop is going. Can I level up the remaining ground to the existing slab height and then pour over that? The plans call for a 4" thick slab with a 12"x12" footing around the perimeter of the building.