Tscott
Well-known member
I'm considering doing some concrete work solo. I've got 2 individual pours. The first is a 35' section of sidewalk and the second is an 8' x 20' slab that will be poured adjacent to an existing driveway slab. If I do this I will likely have no help for the pour so I am a bit hesitant to pull the trigger on this project.
My biggest concern is time. If I try to pour them both with the same truck, I am afraid I'll run out of working time and ruin the finish. I plan to start with the sidewalk and screed it level as I pour and then leave it to pour the slab the same way. Once the slab is poured and leveled I will bounce back to the sidewalk to float it and do the edges. Then I'll move back to the slab to float and edge it. Then back to the sidewalk for the brush finish and then to the slab for its finish.
I plan to do this in about 2 weeks so temps will be in the mid 70's to low 80's unless we get a freak heat wave. Rough math puts me at around 9 yards for the whole job. How long will concrete take to set in those temps? Am I crazy to attempt this on my own?
Tom
My biggest concern is time. If I try to pour them both with the same truck, I am afraid I'll run out of working time and ruin the finish. I plan to start with the sidewalk and screed it level as I pour and then leave it to pour the slab the same way. Once the slab is poured and leveled I will bounce back to the sidewalk to float it and do the edges. Then I'll move back to the slab to float and edge it. Then back to the sidewalk for the brush finish and then to the slab for its finish.
I plan to do this in about 2 weeks so temps will be in the mid 70's to low 80's unless we get a freak heat wave. Rough math puts me at around 9 yards for the whole job. How long will concrete take to set in those temps? Am I crazy to attempt this on my own?
Tom
