Simplytodd
Well-known member
Hello,
Just like a lot of other first time poster I have been lurking around in the background trying to absorb all the great info this site has to offer. Anyway I am getting ready to break ground on my shop and had a few questions about control joints in a new slab. The following is the specs that the contractor provided after our initial consultation.
Slab is 30'x62'
Shop is 30'x50' feet enclosed with the remaining 12' being covered parking on one of the end walls.
There will be 244' of interior and exterior beams.
Beams will be 24"x12" with 4 5/8" rebar with 3/8" stirrups 24"OC
Pour will be continuous 5" thick of 4000 psi concrete.
Slab mat will be 3/8" rebar 12" OC supported by chairs.
I will be meeting the contractor this coming Tuesday to review site prep and to nail down a more exact figure on pricing. The initial quote and specs didn't include saw cuts. I have come to the conclusion that I would like to include them in my build. Now on to the questions.
First. From the searching I have done with the thickness that the slab will be poured too a 10'x10' saw cut pattern seems to be the consensus. That would leave me with a grid of 18 10'x10' squares. That seems like a lot. I don't mind the cuts so much because they can be filled with caulk or some other material to keep dirt and general nasties out but I believe they charge by the foot and that's 274' of cuts. Would a rectangular pattern of 20'x10' be okay considering the amount of rebar being placed in the slab?
Second. I will be placing a 9k lift in one of the bay's and the columns for the lift would bridge between two separate squares using the 10'x10' pattern. Is this a no go or perfectly acceptable? Also I couldn't seem to find a definitive answer on pouring a thicker pad depth for the area under the lift columns. Something like a 4'x4' area poured to a 10"-12" depth? There were about as many people saying that this can cause cracking in the slab as there were saying that they want the added security. The lift manufacturers mostly call for 4" @ 3500 psi so I would seem to be okay as is without the extra concrete.
Any help or insights will be greatly appreciated.
Just like a lot of other first time poster I have been lurking around in the background trying to absorb all the great info this site has to offer. Anyway I am getting ready to break ground on my shop and had a few questions about control joints in a new slab. The following is the specs that the contractor provided after our initial consultation.
Slab is 30'x62'
Shop is 30'x50' feet enclosed with the remaining 12' being covered parking on one of the end walls.
There will be 244' of interior and exterior beams.
Beams will be 24"x12" with 4 5/8" rebar with 3/8" stirrups 24"OC
Pour will be continuous 5" thick of 4000 psi concrete.
Slab mat will be 3/8" rebar 12" OC supported by chairs.
I will be meeting the contractor this coming Tuesday to review site prep and to nail down a more exact figure on pricing. The initial quote and specs didn't include saw cuts. I have come to the conclusion that I would like to include them in my build. Now on to the questions.
First. From the searching I have done with the thickness that the slab will be poured too a 10'x10' saw cut pattern seems to be the consensus. That would leave me with a grid of 18 10'x10' squares. That seems like a lot. I don't mind the cuts so much because they can be filled with caulk or some other material to keep dirt and general nasties out but I believe they charge by the foot and that's 274' of cuts. Would a rectangular pattern of 20'x10' be okay considering the amount of rebar being placed in the slab?
Second. I will be placing a 9k lift in one of the bay's and the columns for the lift would bridge between two separate squares using the 10'x10' pattern. Is this a no go or perfectly acceptable? Also I couldn't seem to find a definitive answer on pouring a thicker pad depth for the area under the lift columns. Something like a 4'x4' area poured to a 10"-12" depth? There were about as many people saying that this can cause cracking in the slab as there were saying that they want the added security. The lift manufacturers mostly call for 4" @ 3500 psi so I would seem to be okay as is without the extra concrete.
Any help or insights will be greatly appreciated.
