My wife had a new sidewalk section poured, and I didn't do my research ahead of time.

They poured it today, and it's over 100 degrees outside and it's not covered or anything.

Am I supposed to keep the surface wet? What about cover it with plastic?
 
To avoid these ads, REGISTER NOW!

jack stand

Well-known member
Joined
Feb 29, 2012
Messages
3,400
Location
Lakes Region Maine
Wet it occasionally until you go to bed. Plastic can leave marks depending on how far along your concrete is. Burlap with a small flow of water across it is what I'm familiar with, not sure if this is done today with all the chemicals available.
Someone that's a concrete professional should be along here but the clock is running.
 
OP
J

JackOfDiamonds

Well-known member
Joined
Jul 31, 2020
Messages
718
Location
Idaho (USA)
I decided to spray it with the hose a little bit after checking that it was sorta hard.

In this sun, I pretty much soak it down and it's starting to turn grey/dry again in 20 minutes or so. Do I need to have one of my kids keep it moist constantly or just re-wet it every couple hours? Is it bad to let it dry and then re-wet it?
 

jack stand

Well-known member
Joined
Feb 29, 2012
Messages
3,400
Location
Lakes Region Maine
I would say just wet it every hour or so. I do know that a slower curing is desired, but don't know what the (possible) consequences are. It's just a sidewalk and I'm sure overthinking and worrying is probably just something we have to do 😆.
 

marak

Well-known member
Joined
Jan 26, 2015
Messages
339
Location
Anchorage, Alaska
If no sealer applied then you will want to keep it wet. If fresh concrete dries out too much then hydration (curing) will stop. For a sidewalk, this is not the end of the world. After hosing it down, I like to place 6-mil polyethylene sheeting on top of the concrete and keep the surface of the concrete saturated to wet. Consider keeping the surface wet for 3 to 6 days. Make sure the poly sheeting lays flat as wrinkles can cause discoloration, if I recall correctly.
 

Half-fast eddie

Well-known member
Joined
Jul 10, 2021
Messages
1,479
Location
Virginia
How big is the section? You said sidewalk … not a structural element. Minimum psi is probably more than enough. Did they cut an6 control joints?
 
To avoid these ads, REGISTER NOW!

brownbagg

Well-known member
Joined
Mar 20, 2006
Messages
5,208
My wife had a new sidewalk section poured, and I didn't do my research ahead of time.

They poured it today, and it's over 100 degrees outside and it's not covered or anything.

Am I supposed to keep the surface wet? What about cover it with plastic?
yes
 

nadogail

Well-known member
Joined
Jan 23, 2009
Messages
32,253
Location
Coronado, CA
When I lived in Spain we would spread Sand on a new slab and moisten it for a few days, after which the sand was used for the mix when we laid the structural tile and plastered the walls.
 