cavediver
Member
Hi Gang,
I am still considering the porcelain tile route in my workshop, and will probably be tackling it later this fall. In preparation, I am trying to develop a game plan, and prepare myself (mentally?) for the task at hand.
The shop is 20x30 with a concrete slab that was poured 6" or better with 6'x10' pads that are 16" thick for a two post lift. This was poured early last summer and shows some minor shrinkage cracks but nothing significant. Unfortunately, it didn't turn out exactly how I wanted it to so I have a little more work to complete before laying tile.
The floor was poured level, the front (West - garage door), and the rear (east) are essentially at the same height - this is the 30' length. I would like to prep the floor so that I have the existing height at the garage door (plus the Schluter Reno Ramp transition to tile), and approximately 1/8"/ft slope to the east end (30' away). So that's 3.75" to be raised at the far end.
I have 12'6" ceilings and can afford to loose the 4" along the east wall in order to gain the water shedding benefits (I have puddles and constantly wet areas from the cars defrosting this winter in the shop).
So I need a Game plan:
I was thinking of ripping some 2x4's down with a taper that is 1/8" per foot and attaching them temporarily to the existing floor as a guide to screed "something" to the final slope. I was thinking of placing the "2x4 ramp guides" about 4-5 feet apart. Then when the "something" sets up, pull the ramps out and fill up the remaining channels with more "something".
What product should this "something" be? Will normal concrete be resilient enough for this application? Should it be thinset from the 0-->2" section and then concrete or mortar mix from the 2"-->4" areas?
Location is in Central Ontario, so consideration for moisture and freezing temps is important.
Thanks for your input - John
I am still considering the porcelain tile route in my workshop, and will probably be tackling it later this fall. In preparation, I am trying to develop a game plan, and prepare myself (mentally?) for the task at hand.
The shop is 20x30 with a concrete slab that was poured 6" or better with 6'x10' pads that are 16" thick for a two post lift. This was poured early last summer and shows some minor shrinkage cracks but nothing significant. Unfortunately, it didn't turn out exactly how I wanted it to so I have a little more work to complete before laying tile.
The floor was poured level, the front (West - garage door), and the rear (east) are essentially at the same height - this is the 30' length. I would like to prep the floor so that I have the existing height at the garage door (plus the Schluter Reno Ramp transition to tile), and approximately 1/8"/ft slope to the east end (30' away). So that's 3.75" to be raised at the far end.
I have 12'6" ceilings and can afford to loose the 4" along the east wall in order to gain the water shedding benefits (I have puddles and constantly wet areas from the cars defrosting this winter in the shop).
So I need a Game plan:
I was thinking of ripping some 2x4's down with a taper that is 1/8" per foot and attaching them temporarily to the existing floor as a guide to screed "something" to the final slope. I was thinking of placing the "2x4 ramp guides" about 4-5 feet apart. Then when the "something" sets up, pull the ramps out and fill up the remaining channels with more "something".
What product should this "something" be? Will normal concrete be resilient enough for this application? Should it be thinset from the 0-->2" section and then concrete or mortar mix from the 2"-->4" areas?
Location is in Central Ontario, so consideration for moisture and freezing temps is important.
Thanks for your input - John
