bmwpowere36m3
Well-known member
- Joined
- Nov 8, 2012
- Messages
- 1,125
Got my first quote for a 30x30' foundation including site work.
Foundation:
30' x 30' overal size
42" deep footers (12"x24")
10" stem wall, 2' above grade
5" slab
Site Work:
Scrap/pile topsoil from site, plus 1000 sqft of driveway leading to garage
Break 10 CY ledge
Grade/fill ~18" elevation across site
Dig foundation/backfill/compact
Estimates:
10 loads (16 CY/ea) @ $400/ea for foundation infill
5 loads (16 CY/ea) @ $400/ea for driveway
28 CY footer/stem wall @ $125/CY
16 CY slab @ $125/CY
Site Work $6000
Footing & Stem Wall $3360
Slab $1200
Rebar, Wire Mesh, Vapor Barrier Material/Labor $2085
Form Bolts/Ties $185
$13K to contractor, $6K for concrete & $6k for "fill" = 25K total
Getting more estimates... The conundrum is we have a 7K mini-ex and skid-steer. A couple years ago we dug a similar foundation for my father, however he didn't have any ledge. I've tried to attack it with pneumatic jack hammer and 600 lb hydraulic hammer for the mini-ex to slow progress.
The contractor has a 4K hammer for his machine, admittedly a bit big for the job, but its what he has. Downside, he needs to hire to deliver his machine @ $1K roundtrip. If it wasn't for the ledge, he'd bring a smaller machine that he can transport.
I'm debating renting a 40k excavator with 2K hammer for ~$2k and getting the site work done myself.
Foundation:
30' x 30' overal size
42" deep footers (12"x24")
10" stem wall, 2' above grade
5" slab
Site Work:
Scrap/pile topsoil from site, plus 1000 sqft of driveway leading to garage
Break 10 CY ledge
Grade/fill ~18" elevation across site
Dig foundation/backfill/compact
Estimates:
10 loads (16 CY/ea) @ $400/ea for foundation infill
5 loads (16 CY/ea) @ $400/ea for driveway
28 CY footer/stem wall @ $125/CY
16 CY slab @ $125/CY
Site Work $6000
Footing & Stem Wall $3360
Slab $1200
Rebar, Wire Mesh, Vapor Barrier Material/Labor $2085
Form Bolts/Ties $185
$13K to contractor, $6K for concrete & $6k for "fill" = 25K total
Getting more estimates... The conundrum is we have a 7K mini-ex and skid-steer. A couple years ago we dug a similar foundation for my father, however he didn't have any ledge. I've tried to attack it with pneumatic jack hammer and 600 lb hydraulic hammer for the mini-ex to slow progress.
The contractor has a 4K hammer for his machine, admittedly a bit big for the job, but its what he has. Downside, he needs to hire to deliver his machine @ $1K roundtrip. If it wasn't for the ledge, he'd bring a smaller machine that he can transport.
I'm debating renting a 40k excavator with 2K hammer for ~$2k and getting the site work done myself.