Marctrees
Well-known member
Building a 10 x 20 deck... dock at waters edge.
4x6 posts, three rows of 5 each.
Going to put 2x8 beams under joists.
Want to talk about connection of beams to posts.
Sure ... best to cut a shallow rabbet to act as a ledger, then throughbolt or screw to post.
The rabbet cutting is a major PIA over water.
Want to use GK RS 3/8 x 5 to w/o rabbet attach 1 1/2" 2x8 beams to the 4" thickness of the posts.
Posts will continue up to railing height around perimiter, and be flush cut at top of beams in middle row of deck.
Propose slapping "2x8" joist against beam, NO rabbet ledge, and four GRK RSS 3/8 x 5" per connection.
Thoughts ?
Marc
4x6 posts, three rows of 5 each.
Going to put 2x8 beams under joists.
Want to talk about connection of beams to posts.
Sure ... best to cut a shallow rabbet to act as a ledger, then throughbolt or screw to post.
The rabbet cutting is a major PIA over water.
Want to use GK RS 3/8 x 5 to w/o rabbet attach 1 1/2" 2x8 beams to the 4" thickness of the posts.
Posts will continue up to railing height around perimiter, and be flush cut at top of beams in middle row of deck.
Propose slapping "2x8" joist against beam, NO rabbet ledge, and four GRK RSS 3/8 x 5" per connection.
Thoughts ?
Marc