We need updates!
Well I would say that the biggest update is that it is a comfortable 60 degrees inside! The heat was hooked up at the end of October.
The grass was planted in September & was coming up nicely before the cold set it.
All the trim has been installed downstairs so it is pretty much complete as far as the construction goes.
The bathroom is finished as well as the sink & water to the kitchenette upstairs.
Still have to finish the stairs & install trim & flooring upstairs.
Will try to get some pictures soon.
Thanks for the interest.
Todd