I am wondering if I'm being too **** with a contractor.
My position is a Resident Engineer overseeing FAA projects.
Project: .5 mile pier into a river
Issue: Shop drawings that were submitted for the 1 mile of handrail note a 0.25 nominall exspansion joint between sections of railing. Accomplished with a slip fit joint. Two months ago when the handrail install began I brought to the PM's attention the fact that the joints were not consistant from the top rail to the bottom rail. Some were 0.25 at top, .50 -.75 at bottom or vise versa. This was approximatly 3 sections into the install. I was pretty much told to kick rocks and go pound sand.
The fix would have been to test fit sections and remove with a port-a-band the offending material. Instead he let his crews "stack" the problem. Now 1,800 feet into the problem he wants to argue the definition of "nominal". I am allowing him up to .375 which constitutes a 50% "nominal" margin. The fix now is to remove 1.5" or better of material and weld in a correct sized piece to better close the gaps = time=$$$
If he would have addressed the issue 2 months ago I would have been more apt to forgive further into the project.
Pride in workmanship is a dead art.
So am I right.....or just a pr#ck??? Be honest I can take it.
My position is a Resident Engineer overseeing FAA projects.
Project: .5 mile pier into a river
Issue: Shop drawings that were submitted for the 1 mile of handrail note a 0.25 nominall exspansion joint between sections of railing. Accomplished with a slip fit joint. Two months ago when the handrail install began I brought to the PM's attention the fact that the joints were not consistant from the top rail to the bottom rail. Some were 0.25 at top, .50 -.75 at bottom or vise versa. This was approximatly 3 sections into the install. I was pretty much told to kick rocks and go pound sand.
The fix would have been to test fit sections and remove with a port-a-band the offending material. Instead he let his crews "stack" the problem. Now 1,800 feet into the problem he wants to argue the definition of "nominal". I am allowing him up to .375 which constitutes a 50% "nominal" margin. The fix now is to remove 1.5" or better of material and weld in a correct sized piece to better close the gaps = time=$$$
If he would have addressed the issue 2 months ago I would have been more apt to forgive further into the project.
Pride in workmanship is a dead art.
So am I right.....or just a pr#ck??? Be honest I can take it.
