I'll usually come in after the footings are poured. I'll take some rigid foam board and block a hole out in the bottom of the stem wall forms, right on top of the footing. Knock the foam out after it's poured and run the conduit through.
If this building is detached, you'll need a ufer ground. So make sure a piece of rebar gets stubbed up out of the footings, up through the stem wall and into a stud cavity. Try to do this under the panel if possible. If it's not possible, then just run your ground wire from the panel to where the rebar is stubbed up. An inspector needs to look at the ufer and tag it before the footings are poured. Here in Oregon the building inspector is the one that tags it.