BrerHair
Member
How about for a 14,000 SF luxury home?
1999, the turn-key bids were coming in around $110,000 for the poured concrete foundation walls and my boss says to me: You can do this, can't you?
I knew that I could, if I had enough labor. What if we use our eight man framing crew for labor?
But would we save money? I thought probably yes, the boss just knew we would save a ton.
So, I set out to do it. We had, of course, a structural engineer design the foundation walls, specifying wall thickness, some 14" thick, mostly 10" thick, and steel rebar reinforcement specs.
I designed a simple panel form built with 2x4's and 3/4" CDX plywood. Can't remember how many form panels we built, but it was a lot, something around 100, probably more. Have my original notes in a box in the attic somewhere with answers to questions like this.
The huge (approx. 5,000 SF) basement was a split level basement. Half had 12 ft. high poured walls and the other half had 19 ft. high walls, for an indoor half-court basketball court.
Here's an overview look at it:
Left half of pic above is 12 ft. high walls. right half are 19 ft. high walls in process - you can make out the 19 ft. high rebar but not all of the form panels are in place.
So, each form panel was 4' x 8', a 3/4" cdx plywood sheet backed-up by a 2x4 frame.
Here is a pic of the footing pour and you can see the many pre-made form panels stacked flat on the ground, covered with plastic:
Here is a close-up shot of a panel. We red-head bolted the bottom of the bottom-most panel to the footing and we nailed the panels to adjoining panels. Note also the "wall ties", the small diameter steel rods connecting panels on one side of the wall to the panels on the other side of the wall. These wall ties were held in place with the metal plates that you see in the pic, the ties were manufactured for a certain wall thickness (10", 14", etc.) and we had to add 2x4 blocks to give the metal plates something to grab ahold of:
Here you can see the wall ties, called "snap ties" by the manufacturer because after the walls are poured and the forms are stripped, you take a hammer and snap off the part of the tie sticking out of the poured concrete wall:
Note in pic above that the vertical rebar looks awful close to one side of the forms. Engineer specs called for 2" cover, meaning the vertical rebar had to be 2" from a specified wall side. Doesn't look like 2" in this pic, but we made sure we had them spaced properly before we poured. This pic is looking down on a 10" thick wall section.
Here is another pic of footing pour. Note all the pre-made form panels under plastic. The group of hombres are standing in the 12 ft. high basement half. Note the makeshift ladder going down to the 19 ft. high basement half in foreground. Note also the footing bulkheads where footing jumps down the 7 feet from 12' half to 19' half:
Here is a progress pic showing some of the forms already erected in place and some of the forms still stacked on the ground:
Another footing pour pic:
As you can see, we tied an assload of steel rebar.
Here are a few more progress pics:
This was one ******* job site!
We had to leave out a 12' high wall section so that we could get machinery down into the basement for backfill and slab plumbing purposes. Here you can see the missing wall section:
We used hand sprayers to spray some oil on concrete side of plywood forms to prevent the concrete from sticking to the plywood. Can't remember exactly what we used but it was whatever our Charlotte concrete supplier Tucker-Kirby Co. recommended.
We also tried to vibrate the wet concrete with hand vibrators to prevent honeycombing, but honestly it was like ******* in the ocean, the ******** wand did not go far enough down and it was difficult what with all the rebar etc. Better than nothing I guess, but we also knew that all of the walls would end up covered with finished material, the entire basement was finished.
Here is one of the vibrators being moved to another spot during the pour:
Here you can see the J-bolts sticking out at top of poured wall:
And here you can see rebar loops sticking out of the top of poured walls for either adjacent garages or porches:
People ask all the time, in this business, "Can you do this or that?" "Can we add a [fireplace; built-in grill; double door; interior golf putting room; home theater with rows of seats that slope down to the screen like a real theater; etc.]?" There is no limit to what could be added (or deleted). The answer is always the same: we can do anything, the real questions are a) how much will it cost and b) how long will it take?
I like to tell folks "We could build a scale model of the Golden Gate Bridge out of 2x4." It would take boatloads of 2x4 and countless thousands of man hours, but it could be done.
This poured wall project was a minor lesson in " . . . give us enough 2x4's".
We braced the wall forms simply by gut feel, there was certainly nothing scientific about it. We had seen our share of collapses over the years to know that we better brace the Bejesus out of it.
Here's one I like, looking at part of the 19' high walls:
There's more to the story but this is all I can do for now.
Enjoy, you DIY-ers.
1999, the turn-key bids were coming in around $110,000 for the poured concrete foundation walls and my boss says to me: You can do this, can't you?
I knew that I could, if I had enough labor. What if we use our eight man framing crew for labor?
But would we save money? I thought probably yes, the boss just knew we would save a ton.
So, I set out to do it. We had, of course, a structural engineer design the foundation walls, specifying wall thickness, some 14" thick, mostly 10" thick, and steel rebar reinforcement specs.
I designed a simple panel form built with 2x4's and 3/4" CDX plywood. Can't remember how many form panels we built, but it was a lot, something around 100, probably more. Have my original notes in a box in the attic somewhere with answers to questions like this.
The huge (approx. 5,000 SF) basement was a split level basement. Half had 12 ft. high poured walls and the other half had 19 ft. high walls, for an indoor half-court basketball court.
Here's an overview look at it:
Left half of pic above is 12 ft. high walls. right half are 19 ft. high walls in process - you can make out the 19 ft. high rebar but not all of the form panels are in place.
So, each form panel was 4' x 8', a 3/4" cdx plywood sheet backed-up by a 2x4 frame.
Here is a pic of the footing pour and you can see the many pre-made form panels stacked flat on the ground, covered with plastic:
Here is a close-up shot of a panel. We red-head bolted the bottom of the bottom-most panel to the footing and we nailed the panels to adjoining panels. Note also the "wall ties", the small diameter steel rods connecting panels on one side of the wall to the panels on the other side of the wall. These wall ties were held in place with the metal plates that you see in the pic, the ties were manufactured for a certain wall thickness (10", 14", etc.) and we had to add 2x4 blocks to give the metal plates something to grab ahold of:
Here you can see the wall ties, called "snap ties" by the manufacturer because after the walls are poured and the forms are stripped, you take a hammer and snap off the part of the tie sticking out of the poured concrete wall:
Note in pic above that the vertical rebar looks awful close to one side of the forms. Engineer specs called for 2" cover, meaning the vertical rebar had to be 2" from a specified wall side. Doesn't look like 2" in this pic, but we made sure we had them spaced properly before we poured. This pic is looking down on a 10" thick wall section.
Here is another pic of footing pour. Note all the pre-made form panels under plastic. The group of hombres are standing in the 12 ft. high basement half. Note the makeshift ladder going down to the 19 ft. high basement half in foreground. Note also the footing bulkheads where footing jumps down the 7 feet from 12' half to 19' half:
Here is a progress pic showing some of the forms already erected in place and some of the forms still stacked on the ground:
Another footing pour pic:
As you can see, we tied an assload of steel rebar.
Here are a few more progress pics:
This was one ******* job site!
We had to leave out a 12' high wall section so that we could get machinery down into the basement for backfill and slab plumbing purposes. Here you can see the missing wall section:
We used hand sprayers to spray some oil on concrete side of plywood forms to prevent the concrete from sticking to the plywood. Can't remember exactly what we used but it was whatever our Charlotte concrete supplier Tucker-Kirby Co. recommended.
We also tried to vibrate the wet concrete with hand vibrators to prevent honeycombing, but honestly it was like ******* in the ocean, the ******** wand did not go far enough down and it was difficult what with all the rebar etc. Better than nothing I guess, but we also knew that all of the walls would end up covered with finished material, the entire basement was finished.
Here is one of the vibrators being moved to another spot during the pour:
Here you can see the J-bolts sticking out at top of poured wall:
And here you can see rebar loops sticking out of the top of poured walls for either adjacent garages or porches:
People ask all the time, in this business, "Can you do this or that?" "Can we add a [fireplace; built-in grill; double door; interior golf putting room; home theater with rows of seats that slope down to the screen like a real theater; etc.]?" There is no limit to what could be added (or deleted). The answer is always the same: we can do anything, the real questions are a) how much will it cost and b) how long will it take?
I like to tell folks "We could build a scale model of the Golden Gate Bridge out of 2x4." It would take boatloads of 2x4 and countless thousands of man hours, but it could be done.
This poured wall project was a minor lesson in " . . . give us enough 2x4's".
We braced the wall forms simply by gut feel, there was certainly nothing scientific about it. We had seen our share of collapses over the years to know that we better brace the Bejesus out of it.
Here's one I like, looking at part of the 19' high walls:
There's more to the story but this is all I can do for now.
Enjoy, you DIY-ers.
