Next it was time to finish the room. Insulation, vapor barrier, then plywood.

Once plywood was up, 3 coats of kilz was applied, followed by 3 coats of paint.

IMAG2028.jpg

IMAG2029.jpg

IMAG2030.jpg

IMAG2031.jpg

IMAG2032.jpg

IMAG2051.jpg

IMAG2053.jpg
 
OP
S

stngfever

Well-known member
Joined
Apr 2, 2013
Messages
89
Location
West Michigan
More updates:

It was time to add more cement with an 8 foot addition to the front apron and a sidewalk on North side of building to connect entry door with apron:

IMAG2329.jpg

IMAG2330.jpg

IMAG2331.jpg

IMAG2332.jpg

IMAG2333.jpg

IMAG2334.jpg
 
OP
S

stngfever

Well-known member
Joined
Apr 2, 2013
Messages
89
Location
West Michigan
Then onto the West and final wall for insulation and OSB install.

It was time to stop procrastinating the electrical termination in the panel!

IMAG2335.jpg

IMAG2336.jpg

IMAG2337.jpg

IMAG2338.jpg

IMAG2339.jpg
 
To avoid these ads, REGISTER NOW!
OP
S

stngfever

Well-known member
Joined
Apr 2, 2013
Messages
89
Location
West Michigan
Also on West wall was terminations for Ethernet (Cat5 from house), Coax (from house and to 2 tv wall locations) and 2 HDMI cables.

IMAG2353.jpg

IMAG2354.jpg

IMAG2355.jpg

IMAG2357.jpg

IMAG2358.jpg
 
OP
S

stngfever

Well-known member
Joined
Apr 2, 2013
Messages
89
Location
West Michigan
IMAG2360.jpg

IMAG2362.jpg

IMAG2363.jpg

Once west wall was done, time for lower steel test install.

IMAG2364.jpg

Now onto ceiling, Stapled R-11 paperback to trusses, then a Cris-cross on top of that using a layer of R-19 and R-11 (3 layers in total).

IMAG2365.jpg

IMAG2366.jpg

IMAG2368.jpg
 
OP
S

stngfever

Well-known member
Joined
Apr 2, 2013
Messages
89
Location
West Michigan
Now it was time to start the ceiling:

IMAG2370.jpg

IMAG2371.jpg

IMAG2372.jpg

Decided for a break on the ceiling to install some lower wall steel:

IMAG2382.jpg

IMAG2383.jpg

One of my criagslist finds included some electrical items and amongst them was this "Pull Alarm" and some strobe/fire alarms. I decided to hook this up to a transformer more for a "novelty". However, the extinguisher is real.

IMAG2384.jpg
 
OP
S

stngfever

Well-known member
Joined
Apr 2, 2013
Messages
89
Location
West Michigan
Next up is the installation of 2-5' unistruts (a pair of 8' 2x4's laid on top of truss bottom cords was used to attach the 1/2' threaded rods). These are in place for my Fall activities of deer hunting. One unistrut is for an electric hoist and the other will have some eye bolts installed to hang deer from.

IMAG2408.jpg

IMAG2409.jpg

IMAG2410.jpg

IMAG2413.jpg
 

diypolebarns

Member
Joined
Mar 7, 2010
Messages
17
Location
Arcanum, Ohio
Awesome! Many are the envious men right now drooling over your pics. Enjoy the culmination of the many hours of dreaming, planning, working, and now playing inside your new shop.
 

justin1795

Well-known member
Joined
Aug 7, 2013
Messages
442
Location
blue grass IA
are you just stuffing a little insulation behind your 2x4s? plan on finishing mine similar. was thinking of doing 2x6's but its quite a bit more
 
OP
S

stngfever

Well-known member
Joined
Apr 2, 2013
Messages
89
Location
West Michigan
@diypolebarns - thanks, it certainly is a labor of love

@cheezhead - thanks and it's always great to see other's with the same disease, lol

@justin1795 - I didn't try to stuff any small pieces of insallation behing the 2x4's, I merely used 5 1/2" thick insulation since my posts we're 6x6's
 
To avoid these ads, REGISTER NOW!
Top Bottom