Hello Everyone, and thanks to all of you for helping others. - I have searched and searched this forum for an answer to this, but have not found anything similar.
I have a detached building and will be installing a 60A subpanel off my homes 200A main service. - The interior building wiring is now complete and everything inside is now connected to the new 60A breaker panel. - The final step is to dig a trench and run my copper #4/3 w/ground from the house to the building. -
I am down to 2 questions....,
The building is sided with metal PBR panels. Is my only option to install an LB box on the outside of the building ? - My electrical penetration is facing the front of my building, so visually, I'd prefer something that might be a little less obvious when driving up to it.
Are there any NEC reqirements how far from the ground the penetration must be ? My breaker panel is inside and 54" above the finished floor. Can I make the exterior penetration 10" from the ground and run 44" of pvc conduit inside the building up to the breaker panel, or do I need to mount the LB box at the same height as the panel.
Thanks in advance !
Those are my only 2 electrical related questions, but if anyone may have any tips/advice for digging a 100' trench from house to building, that would be appreciated as well. -
--
I have a detached building and will be installing a 60A subpanel off my homes 200A main service. - The interior building wiring is now complete and everything inside is now connected to the new 60A breaker panel. - The final step is to dig a trench and run my copper #4/3 w/ground from the house to the building. -
I am down to 2 questions....,
The building is sided with metal PBR panels. Is my only option to install an LB box on the outside of the building ? - My electrical penetration is facing the front of my building, so visually, I'd prefer something that might be a little less obvious when driving up to it.
Are there any NEC reqirements how far from the ground the penetration must be ? My breaker panel is inside and 54" above the finished floor. Can I make the exterior penetration 10" from the ground and run 44" of pvc conduit inside the building up to the breaker panel, or do I need to mount the LB box at the same height as the panel.
Thanks in advance !
Those are my only 2 electrical related questions, but if anyone may have any tips/advice for digging a 100' trench from house to building, that would be appreciated as well. -
--