This is a great forum, my first post. I am going to be installing electrical in my pole barn about 150 ft from house. I have a 200 amp service panel that is full in house with a sub panel next to it. The sub panel is empty so I wanted to feed my barn with it. I am running 100 amps 240V to the barn. #2 Cu THWN in 1 1/2" in shd 40 pvc.
I plan to run 4 wires, 3 - 2 Cu THWN (2 Hots and Neutral) and a 8 bare Cu for equipment ground. in 1 1/2" in shd 40 pvc. I have the ground and neutral isolated in the sub panel in the basement and plan to have the isolated in pole barn as well. Where would the equipment ground be connected in the basement sub panel, the ground bus ? That is what makes sense to me but wanted to make sure.
Thank you for your feedback.
I plan to run 4 wires, 3 - 2 Cu THWN (2 Hots and Neutral) and a 8 bare Cu for equipment ground. in 1 1/2" in shd 40 pvc. I have the ground and neutral isolated in the sub panel in the basement and plan to have the isolated in pole barn as well. Where would the equipment ground be connected in the basement sub panel, the ground bus ? That is what makes sense to me but wanted to make sure.
Thank you for your feedback.
) is number one. When stripped the wire, DO NOT cut into the conductor as it will score the soft aluminum and create a hot spot, number two, make sure you sent a maintenance schedule to service these terminations and retorque them. As they WILL expand and contract and loosen in the lug. If it where me I would just do copper and be done. But what do I know I'm just an electrician