Been lurking for a very long time. About to start my garage build and have everything pretty much finalized.
I'm going to get my styrofoam this weekend for the underslab insulation. Then groundbreaking will occur!
I'm building a 40x42' garage with a 2 foot in jog. Front will have a 12' and 16' door with another 12' at the rear.
I'm pouring 2 pads that will be used for a hoist sometime in the future.
My biggest concern that i'm trying to figure out is placement of floor drains and looking for input. Below are some screenshots of the layout.
The red DOTS on the pex loop layout is where i'm thinking for rough layout estimates. One in the middle of where the hoist will go, middle of garage and then middle of the 2nd bay.
Anyone with experience for good drain layouts want to chime in!
Thank you.
Chris
I'm going to get my styrofoam this weekend for the underslab insulation. Then groundbreaking will occur!
I'm building a 40x42' garage with a 2 foot in jog. Front will have a 12' and 16' door with another 12' at the rear.
I'm pouring 2 pads that will be used for a hoist sometime in the future.
My biggest concern that i'm trying to figure out is placement of floor drains and looking for input. Below are some screenshots of the layout.
The red DOTS on the pex loop layout is where i'm thinking for rough layout estimates. One in the middle of where the hoist will go, middle of garage and then middle of the 2nd bay.
Anyone with experience for good drain layouts want to chime in!
Thank you.
Chris
Last edited: