jmiller_2308
Well-known member
I have been going through delay after delay with the GC I'm trying to use to build my garage addition and I am now wondering whether it is even feasible to get it shelled before the snow flies.
Keeping it simple, think of the garage as a 25x28 by 11' high addition to an existing garage. It is a bit more complicated but I think focusing on that size makes the question easier to ask.
Some additional info:
I'm looking for the GC to get the thing buttoned up on the outside before the snow flies which around here could come as early as the end of October but usually starts in November. (Shakopee, MN - south of Minneapolis).
He would do the concrete inside but I'd do all remaining insulation, walls, electric, heat, cool, etc. I also would be responsible for outside driveway extension but if he takes too long the tar plants will shut down before that can be done this year.
Finally onto the time frame. I harassed him for final numbers and schedules last Friday and he told me he was just finishing up with the truss people and that I should get something this week. I told him how anxious I was to have this complete before the snow flies and he said he thought the excavation would start early September and that that would leave plenty of time to complete before October. Is this for real
I made the following guestimates and I just don't see it happening in his timeframe so hopefully somebody can let me know if I'm close or if this guy might actually know a thing or two that I don't.
Assume starting Sept 1.
I think a lot of the numbers above are very optimistic, especially considering that inspections happen at whatever rate they choose. Even with these optimistic guesses this still brings me to the middle of October so if my guess are wrong, he starts later than 9/1, inspections slow us down, etc. it really seems to me that this thing can't possibly be completed until November at least, and that is prime snow time.
Any opinions from you folks as to whether my GC might actually get it done before the snow?
Keeping it simple, think of the garage as a 25x28 by 11' high addition to an existing garage. It is a bit more complicated but I think focusing on that size makes the question easier to ask.
Some additional info:
- It is an addition that shares one wall.
- The roof is higher than the existing so there is an over-roofing component that ties them together.
- The roof is a hip and the overoof simply extends the existing roof into the new hip.
- roof is being built with trusses.
- Attached to the house so there are footings and block work.
- The property is fairly flat so excavation is fairly minimal beyond digging for footings.
- Outside siding is stucco with some detail work.
- One 8x16 garage door in front, 1 new man door into existing garage, 1 reused garage door at rear of the building, 3 windows and a thru wall a/c hole.
- Soffits are rough cedar and will need staining hopefully before it is too cold.
I'm looking for the GC to get the thing buttoned up on the outside before the snow flies which around here could come as early as the end of October but usually starts in November. (Shakopee, MN - south of Minneapolis).
He would do the concrete inside but I'd do all remaining insulation, walls, electric, heat, cool, etc. I also would be responsible for outside driveway extension but if he takes too long the tar plants will shut down before that can be done this year.
Finally onto the time frame. I harassed him for final numbers and schedules last Friday and he told me he was just finishing up with the truss people and that I should get something this week. I told him how anxious I was to have this complete before the snow flies and he said he thought the excavation would start early September and that that would leave plenty of time to complete before October. Is this for real

I made the following guestimates and I just don't see it happening in his timeframe so hopefully somebody can let me know if I'm close or if this guy might actually know a thing or two that I don't.
Assume starting Sept 1.
- excavation including digging for footings - 2 days
- footings - need to be poured, hard before working on them, and inspected - 5 days
- block work - needs to be completed after footings and set before framing can begin - 5 days
- framing including sheathing the roof - 10 days
- roofing - 2 days
- cement floor - 1 day
- garage doors and finish work - 2 days
- stucco scratch coat - needs to cure before next - 5 days
- stucco brown coat - needs to cure before next - 5 days
- stucco finish coat - 1 day
- final grade 1 day
- site clean up (dumpster, etc) - 1 day
I think a lot of the numbers above are very optimistic, especially considering that inspections happen at whatever rate they choose. Even with these optimistic guesses this still brings me to the middle of October so if my guess are wrong, he starts later than 9/1, inspections slow us down, etc. it really seems to me that this thing can't possibly be completed until November at least, and that is prime snow time.
Any opinions from you folks as to whether my GC might actually get it done before the snow?
