Above 1200 Sq/FT Georgia 30x60x12 Pole Barn

Wokspaces above 1200 squarefeet.

MikeGA

Active member
Joined
Jun 16, 2025
Messages
25
Name is Mike.
New to Georgia from California.
In the process of building new shop on my property. as stated it is a 30x60x12 pole barn. Has the 3 10x10 roll up doors, just the one man door and 8 windows.
Plan is for a 4 post and 2 post lift
Floor is 6" thick with a section in the center 10x40 that was poured 12" thick for mounting of 2 post rack(s). 4000psi concrete. The concrete crew did screw up and cut control joints in the wrong place in the 10x40 section and working with them about a fix for that. one 2 post rack bolt will fall on the saw cut.
The plan as of now is to use Ghost Shield 8510 on the concrete.
Still waiting on Electric and water to be run to the shop.
I have 12 Hyperlite High bay lights to mount on the inside 4 rows of 3 is the planned lay out.
Will update with more pictures but these are as it sits today.1000002039.jpg1000002040.jpg
 
To avoid these ads, REGISTER NOW!

DrinkMan

Well-known member
Joined
Sep 13, 2020
Messages
1,252
Location
Georgia, USA
I'm in Harlem near Augusta. Where are you at?
I will be filling it with all the **** from my auto repair business I closed out in California. Hope there will be room for my truck and couple other projects, and some regular work.

Our primary residence is north east metro Atlanta (far north east). Near Road Atlanta and Braselton. We also spend significant time in the N.GA mountains and Coastal GA (St Simons). Basically - just travel the state on the back roads.

That truck looks great. Can't wait to read more about it and your other projects here.
 
OP
M

MikeGA

Active member
Joined
Jun 16, 2025
Messages
25
Progress has been slow. I was out in California for 3 weeks
Been waiting on Electric and Water.
I did get the floor sealed.
I used Ghostshield products. I used the 4500 and 2 applications of the 8510.
Put the 4500 down last week and waited 5 days for the 8510 which was applied over 2 days.
I'm hope the electrician will be showing up this week sometime.
I will be finally able to unload my 2 U-Haul Uboxes and 26ft truck of stuff from my shop. hope to get a forklift later this week to unload stuff from the truck
First picture is after the 4500 and 1 coat of the 8510
Second Picture is after the 2nd coat of 8510.
I used a total of 10 gallons for the 2 coats of 8510.

Gutters were also installed while I was out of town.
 

Attachments

  • 1000002385.jpg
    1000002385.jpg
    760.2 KB · Views: 53
  • 1000002388.jpg
    1000002388.jpg
    698.5 KB · Views: 76
Last edited:
To avoid these ads, REGISTER NOW!
OP
M

MikeGA

Active member
Joined
Jun 16, 2025
Messages
25
Got most of my **** piled in a few weeks ago, and working on getting it organized slowly.
Also working on Installing my rack. got it set into place by myself. have the right side post bolted down will work on the left side tomorrow. brought this rack from my business out in California. I have also got my High bay lights mounted, have 12 mounted total. Still waiting on Electrical to be installed. Hopefully this week they will be back out.20251122_125237.jpg
 

Attachments

  • 20251215_ rack install.jpg
    20251215_ rack install.jpg
    448.2 KB · Views: 35
OP
M

MikeGA

Active member
Joined
Jun 16, 2025
Messages
25
Thanks JD.
Pretty happy with it overall. still a work in progress and had some issues with the site prep part of the build and still have some work to do there
 
To avoid these ads, REGISTER NOW!
Top Bottom