I have a new 2 post lift and I need to hook up the power. When I built the shop the electrician installed a 240V 30 amp circuit in the ceiling directly above where I am installing the lift. The box is 5 ft. above the top of the lift and 14 ft. above the power unit.
I am thinking about using either 10 gauge wire inside EMT, or MC 10-2 cable. Maybe I could use both by mounting a box to the top of the power side post with 10 gauge wire in EMT running down the column to the power unit and MC cable running up to make the connection to the box on the ceiling.
What would you use?
I am thinking about using either 10 gauge wire inside EMT, or MC 10-2 cable. Maybe I could use both by mounting a box to the top of the power side post with 10 gauge wire in EMT running down the column to the power unit and MC cable running up to make the connection to the box on the ceiling.
What would you use?
Last edited: