NWOhioChevyGuy
Well-known member
OK, well design is 100% done and I have my 3 bids, just need to put the deposit down to get on the schedule for my project.
I currently have about 3 more weeks of prep work for the site before contractor can even think about starting. I also have to get the final numbers from the financial guys.
Floor Plan
By kkeiser at 2010-04-13
Exterior
By kkeiser at 2010-04-13
Detail
By kkeiser at 2010-04-13
Bid I'm going with was $47,000, includes: Concrete, Framing, All Exterior work except paint & Electrical
I will be doing interior work including; wiring, plumbing, flooring, drywall & finishing.

I currently have about 3 more weeks of prep work for the site before contractor can even think about starting. I also have to get the final numbers from the financial guys.
Floor Plan
By kkeiser at 2010-04-13
Exterior
By kkeiser at 2010-04-13
Detail
By kkeiser at 2010-04-13
Bid I'm going with was $47,000, includes: Concrete, Framing, All Exterior work except paint & Electrical
I will be doing interior work including; wiring, plumbing, flooring, drywall & finishing.