To avoid these ads, REGISTER NOW!

Help - Slab does not meetup with poured frost foundation.

seedtime

Well-known member
Joined
Aug 26, 2018
Messages
121
Location
Kenockee Michigan
My slab is being poured tomorrow and the prep work was done today. After the contractors left I noticed that there was 4-5” of sand on the door thresholds. My first picture shows a cutout in the frost wall for a 36” man door, a 16’ garage door, and a 8’ roll up door. All were framed for cement in this exact way. Basically a sand sandwich. I’m no expert, but this looks like a coverup for someone’s mistake.

My concerns are sand washing out creating a void and small animals digging in under the slab. I wasn’t planning on pouring any aprons until my side driveway was installed.


Sent from my iPhone using Garage Journal
 
To avoid these ads, REGISTER NOW!

ConCretin

Well-known member
Joined
Jan 20, 2011
Messages
3,379
Location
Central Maine
It would be more typical to thicken the slab so it bears on the wall below at door openings to help ensure good support at the edge. I’d have them remove the excess soil before they place,
 

mm08822

Well-known member
Joined
Jan 13, 2012
Messages
6,040
Location
NJ
I sure hope those pics are from a few days ago.
I would expect the soil properly graded, compacted, vapor barrier laid and mesh placed before the concrete truck rolls.
 
OP
S

seedtime

Well-known member
Joined
Aug 26, 2018
Messages
121
Location
Kenockee Michigan
I agree with what everybody is saying. I’ve been given The runaround on the vapor barrier that I just gave up. I will be out there on the job site at 6:30 am tomorrow to plead my case. Like I said, I am not a builder, so I spent 2 years finding someone who seemed trustworthy. I never wanted to be that guy to keep bringing up issues.


Sent from my iPhone using Garage Journal
 

like2wheel

Well-known member
Joined
Oct 29, 2014
Messages
1,693
Location
On an as needed basis
I agree with what everybody is saying. I’ve been given The runaround on the vapor barrier that I just gave up. I will be out there on the job site at 6:30 am tomorrow to plead my case. Like I said, I am not a builder, so I spent 2 years finding someone who seemed trustworthy. I never wanted to be that guy to keep bringing up issues.


Sent from my iPhone using Garage Journal

Don't plead your case, demand it be done correctly! There's no going back. Hell, I'd consider getting there at 5:00, & digging it out myself. I'd put down my own plastic too.

Good luck, hope you get something you're satisfied with.
 

mm08822

Well-known member
Joined
Jan 13, 2012
Messages
6,040
Location
NJ
I would insist on vapor barrier especially if there wasn't gravel placed. Both of these items act as a capillary break to reduce moisture drawn into the slab.
 
To avoid these ads, REGISTER NOW!

RPH

Well-known member
Joined
Dec 17, 2006
Messages
4,190
Location
Michigan Thumb
Have you paid for the job yet? The contractor works for you and if he isn’t willing to follow your plan then it’s time to tell him it starts coming off the top. Compacting an$ laying the plastic I’d the bare minimums. Don’t allow this to happen as you will regret this for the rest of time.
 

ConCretin

Well-known member
Joined
Jan 20, 2011
Messages
3,379
Location
Central Maine
Ideally all the details of your slab placement would have been addressed in the bidding and contract phase but even at this late date, I wouldn't allow the contractor to proceed until you are satisfied. You only get one chance at this.

The lack of a vapor barrier is one issue you've mentioned. The purpose of a vapor barrier is to block water vapor from the soil below from migrating through your concrete. While it's always desirable to prevent moisture intrusion, it's primary function is to prevent moisture sensitive floor coverings from failing. If you sure you'll never install epoxy or some other floor covering, it's not vital.

There are a couple other issues I'd be concerned about as well. Give my Guide to Floor Slabs a read if you have a few minutes. Good luck.
 

High5

Well-known member
Joined
May 10, 2014
Messages
72
Location
Washington state
I hope this worked out as well.

Worthy of consideration. If you are paying for this out of pocket and don't feel comfortable confronting your contractor, then you might want to consider hiring a independent inspector to review each phase of this project. It will take the pressure off of you to address issues such as this and your plans will be followed exactly as drawn.
 
OP
S

seedtime

Well-known member
Joined
Aug 26, 2018
Messages
121
Location
Kenockee Michigan
I thought I would update every one on how the pour turned out. Basically I am very pleased with the quality, especially the finish. The cement truck arrived 8:00 am and they started pouring shortly after that. The finishers were working until 3:00 pm. Took longer to set up due to the cooler weather we have been having.

I took the advice from contributors on this thread, and headed out at 6:00 am to dig out the doorways. Fortunately one of the cement guys was already parked out on the street waiting. I explained my concerns and he dug out the sand and re-laid the mesh. The attached pictures show that the pad does contact the footing in all three doorways. It’s hard to see, since there is sand imbedded in the cement. I decided to forgo the vapor barrier, so I will probably just do a Ghost Shield application in the spring.oyte

I am very pleased with the over quality so far. Eating for doors to arrive, pad needs to be sawcut, and some additional fill needs to brought in.
fbda3fd14cdfbb21663168e5d79f3c10.jpg
ebac4fd3fa38a953d8a0e395369e63c9.jpg
ebac4fd3fa38a953d8a0e395369e63c9.jpg



Sent from my iPhone using Garage Journal
 
OP
S

seedtime

Well-known member
Joined
Aug 26, 2018
Messages
121
Location
Kenockee Michigan
I thought I would update everyone on how the pour turned out. Basically I am very pleased with the quality, especially the finish. The cement truck arrived 8:00 am and they started pouring shortly after that. The finishers were working until 3:00 pm. Took longer to set up due to the cooler weather we have been having.

I took the advice from contributors on this thread, and headed out at 6:00 am to dig out the doorways. Fortunately one of the cement guys was already parked out on the street waiting. I explained my concerns and he dug out the sand and re-laid the mesh. The attached pictures show that the pad does contact the footing in all three doorways. It’s hard to see, since there is sand imbedded in the cement. I decided to forgo the vapor barrier, so I will probably just do a Ghost Shield application in the spring.oyte
0b4587b1faaf7c4c1776156d8993a7e7.jpg
a6a0304dea8eef3a2ca14d0c7594c7aa.jpg

I am very pleased with the overall quality of the build so far. Waiting for doors to arrive, pad needs to be sawcut, and some additional fill needs to brought in.
fbda3fd14cdfbb21663168e5d79f3c10.jpg
ebac4fd3fa38a953d8a0e395369e63c9.jpg
ebac4fd3fa38a953d8a0e395369e63c9.jpg



Sent from my iPhone using Garage Journal
 

kaymccampbell

Well-known member
Joined
Feb 27, 2015
Messages
29,603
Location
Upstate New York
I would grab the angle grinder and a diamond wheel and lop those lumps hanging off the slab and overlapping the foundation. I watched similar blobs allow frost heave to lift and crack a slab.
 
To avoid these ads, REGISTER NOW!
Top Bottom