Sixteen days after completing install of an epoxy/polyaspartic garage floor we still have extremely strong odor. Can any of the resident experts tell me when this might fade without further action? Is there anything we can do to accelerate the process? My contractor has done everything I’ve asked of him and is highly apologetic, but I feel we’re both out of tricks now. I love the floor otherwise.
Details: I had a new garage floor slab poured back in early September. After 60 days I brought in a local company to finish the floor. They ground the surface and applied a coat of 95% solids epoxy along with a layer of flake. This coat was thinned slightly (with acetone, I believe) due to cooler temps and odor from this coat was mild. The weather was cool and the slab around 50 - 55 degrees when this occurred.
The next day there was a brief cold snap so we waited an extra day (48 hours total) to apply the top coat. By that time the epoxy was solidly hard and air temp was back in the 50s or so. A coat of polyaspartic clear was then applied. Odor during install of this layer was terrible, as my contractor had warned, but he said the odor would clear in two days or so. It hasn't. The contractor says he’s done other identical floors since mine without the same issue. Here is what we’ve done:
Unfortunately the odor remains strong.
Where would you suggest I go from here? Did we get a bad batch, a poor mix, or something else? Would another coat seal the odor in or simply reset my time? I love the finished product and would like to just be done here, but cannot live with this level of smell forever. (To be clear, the smell is definitely coming off the floor—this isn’t residual in drywall or anything.)
Thanks! (I'll post links to the actual products used momentarily--need to bump up post count)
Details: I had a new garage floor slab poured back in early September. After 60 days I brought in a local company to finish the floor. They ground the surface and applied a coat of 95% solids epoxy along with a layer of flake. This coat was thinned slightly (with acetone, I believe) due to cooler temps and odor from this coat was mild. The weather was cool and the slab around 50 - 55 degrees when this occurred.
The next day there was a brief cold snap so we waited an extra day (48 hours total) to apply the top coat. By that time the epoxy was solidly hard and air temp was back in the 50s or so. A coat of polyaspartic clear was then applied. Odor during install of this layer was terrible, as my contractor had warned, but he said the odor would clear in two days or so. It hasn't. The contractor says he’s done other identical floors since mine without the same issue. Here is what we’ve done:
- Five days of thorough ventilation (air temps of 40 to 70 in the garage, low humidity).
- Ran contractor's propane heater intermittently for six days (maintained air temps of 65-85, slab got to mid-70s)
- Washed floor with mild detergent and warm water
- Ventilated with windows open and fans running for another 5 days (temps in garage in 40s and 50s).
Unfortunately the odor remains strong.
Where would you suggest I go from here? Did we get a bad batch, a poor mix, or something else? Would another coat seal the odor in or simply reset my time? I love the finished product and would like to just be done here, but cannot live with this level of smell forever. (To be clear, the smell is definitely coming off the floor—this isn’t residual in drywall or anything.)
Thanks! (I'll post links to the actual products used momentarily--need to bump up post count)
