It's a flush mount low rise lift. I should start breaking cement this week in my garage and will update the progress here.
Here is the lift fresh out of the box. The lift will go on the other side of this two car garage.
A question for those of you that have this lift. I would like to keep the gaps as tight as possible between the cement and the lift. Would a 1/2" gap around the perimeter of the lift suffice?
Here is the lift fresh out of the box. The lift will go on the other side of this two car garage.
A question for those of you that have this lift. I would like to keep the gaps as tight as possible between the cement and the lift. Would a 1/2" gap around the perimeter of the lift suffice?



What? Why?
It won't allow the fluid to return to the tank therefor the lift won't go down. I'll be on the phone with Bendpak tomorrow for sure 