I had a slab poured in a new garage. It was put on a nice gravel base, wire mesh with two layers of poly. It's 4" of concrete and was poured in September.(New York) The issue is I've been trying get epoxy done on the floor, but the moisture content is still approx 13%. I was told that it needs to be below 3% to do the floor.
I finally had a NG heater installed on Tuesday and hoping that the heater may be my last hope.
Any ideas on what I can/should do?
I finally had a NG heater installed on Tuesday and hoping that the heater may be my last hope.
Any ideas on what I can/should do?