In the initial stages of building this pole barn, my grader cleared a 40x50 compacted pad over a steep area that, to be leveled out, has about a 4ft high 'low side' to it.
My question is- how close to the edge of the pad can the poles be set, right next to the 'drop off'?
The site is clay/soil, compacted well, and will have 4in of crusher before the poles are set.
My grader said he likes about a 5ft perimeter, but I'm trying to turn the building 90 degrees, which might only give about 2.5ft before it gets close to the cliff.
My question is- how close to the edge of the pad can the poles be set, right next to the 'drop off'?
The site is clay/soil, compacted well, and will have 4in of crusher before the poles are set.