Couple of threads got me thinking and I don't think this has ever been asked - especially not with a poll! 
This will serve as how to calculate time to completion:
- concrete is generally 2 days minimum, unless you had it graded, formed, poured and troweled all in 24 hours....
- days to lock up is framing, sheathing, siding, shingles, ALL doors and windows.
- we can't really count interior in the poll as it's too varied, but you can discuss it. I insulated, VB and drywalled mine myself in 3 days.
So, mine was 6.5 days to lock up. 2 days for concrete and 4.5 days to lock up. I haven't heard of too many that went up faster than mine, but we'll see!
This will serve as how to calculate time to completion:
- concrete is generally 2 days minimum, unless you had it graded, formed, poured and troweled all in 24 hours....
- days to lock up is framing, sheathing, siding, shingles, ALL doors and windows.
- we can't really count interior in the poll as it's too varied, but you can discuss it. I insulated, VB and drywalled mine myself in 3 days.
So, mine was 6.5 days to lock up. 2 days for concrete and 4.5 days to lock up. I haven't heard of too many that went up faster than mine, but we'll see!