Hi Team,
They've started the excavation for my 24x26 garage. Monolithic slab, insulated PEX in floor heat.
I'll be installing the insulation and PEX tubing myself after my concrete contractor digs and forms the foundation, then he will come back to install rebar and finish pour. I may even do the rebar. We'll see.
With this timeline, I have to coordinate a family member's trip into town to help me install, and also coordinate my inspections before the pour.
My question is, how long do you think it would take to install the foam? And how long to staple down the PEX?
Below is a picture from the net similar to my end result. If it's from someone on the forums, much appreciated!
Sent from my Pixel 2 using The Garage Journal mobile app
They've started the excavation for my 24x26 garage. Monolithic slab, insulated PEX in floor heat.
I'll be installing the insulation and PEX tubing myself after my concrete contractor digs and forms the foundation, then he will come back to install rebar and finish pour. I may even do the rebar. We'll see.
With this timeline, I have to coordinate a family member's trip into town to help me install, and also coordinate my inspections before the pour.
My question is, how long do you think it would take to install the foam? And how long to staple down the PEX?
Below is a picture from the net similar to my end result. If it's from someone on the forums, much appreciated!

Sent from my Pixel 2 using The Garage Journal mobile app