This is what Bendpak sent me for their 10AC lift. 2 Post asymettrical.
Lift Concrete Requirements
Before installing your new lift, check the following.
1. LIFT LOCATION: Always use architects plans when available. Check layout dimension against floor plan requirements making sure that adequate space is available.
2. OVERHEAD OBSTRUCTIONS: The area where the lift will be located should be free of overhead obstructions such as heaters, building supports, electrical lines etc.
3. DEFECTIVE CONCRETE: Visually inspect the site where the lift is to be installed and check for cracked or defective concrete.
Specifications of concrete must be adhered to. Failure to do so could cause lift failure resulting in personal injury or death.
A level floor is suggested for proper installation and level lifting. Small differences in floor slopes may be compensated for by proper shimming. If a floor is of questionable slope, consider a survey of the site and/or the possibility of pouring a new level concrete slab.
• DO NOT install lift on any asphalt surface or any surface other than concrete.
• DO NOT install lift on expansion seams or on cracked or defective concrete.
• DO NOT install lift on a second / elevated floor without first consulting building architect.
• DO NOT install lift outdoors unless special consideration has been made to protect the power unit from inclement weather conditions.
CONCRETE SPECIFICATIONS
LIFT MODEL CONCRETE REQUIREMENT
7,000 Pound Two Post Models 4 ” Min. Thickness
9,000 Pound Two Post Models 4 ” Min. Thickness
10,000 Pound Two Post Models 4” Min. Thickness
12,000 Pound Two Post Models 6” Min. Thickness
15,000 Pound Two Post Models 6” Min. Thickness
18,000 Pound Two Post Models 6” Min. Thickness
7,000 Pound Four Post Models 4 ” Min. Thickness
12,000 Pound Four Post Models 4 ” Min. Thickness
18,000 Pound Four Post Models 4” Min. Thickness
27,000 Pound Four Post Models 4” Min. Thickness
35,000 Pound Four Post Models 4” Min. Thickness
40,000 Pound Four Post Models 4” Min. Thickness
NOTE: All models MUST be installed on 3000 PSI concrete only conforming to the minimum requirements shown above. New concrete must be adequately cured by at least 28 days minimum.