INTMD8
Well-known member
I have a 36x47 Wick pole building and would like a bit of overhead storage from the front wall to the 2nd truss out.
What I would like to do is add 2 36ft long 1.75thick 14in height LVL beams next to the existing lower chords and frame it in and cover it with plywood.
I'm just looking for a bit of extra room for boxes/tires/etc. Nothing heavy like engines/transmissions.
Is this a possibility and how do I calculate the strength of the LVL's?
Thanks!
What I would like to do is add 2 36ft long 1.75thick 14in height LVL beams next to the existing lower chords and frame it in and cover it with plywood.
I'm just looking for a bit of extra room for boxes/tires/etc. Nothing heavy like engines/transmissions.
Is this a possibility and how do I calculate the strength of the LVL's?
Thanks!

they would only be able to carry about 30-40 psf, certainly not enough for storage loads and definitely not engines! Deflection on a span like that could be significant, as much as an 2"!