So I've built a 28x24 garage and it's turned out great so far. The only thing that is a little irritating, was the guys who poured my grade beam, poured one place an inch low.. I've shimmed the garage, but this leaves a gap.
When I start my siding, i'll have to start at the base of my wall, thus leaving the gap.
What can I do to fill it and make it look nice??

Any thoughts?/


Jared
 
To avoid these ads, REGISTER NOW!

readhead

Well-known member
Joined
Dec 8, 2012
Messages
6,207
Location
Durango, Co.
Non shrink grout. Typicaly the siding will start below the bottom plate so it may cover the gap. I would still grout to provide bearing and keep the critters out.
 