How to get to my 60a sub panel.

Dansz24

Member
Joined
Oct 7, 2018
Messages
7
Location
Mobile al
I am trying to wire a garage addition. I have a outside meter panel combo. I am going to run a 60a sub feed to the new garage addition. It's a fairly short run. I have #4 se cable to run In 1-1/4 schedule 40 conduit. I don't know how to get the cable from the exterior of the garage to the sub pannel.

I have a lb going through the plywood exterior. I can't figure out how to make the 90 upward to get to the sub panel.

Can I run the se cable outside of conduit once inside of the wall cavity?

Thank you for your help
 

Attachments

  • 20181007_115053.jpg
    20181007_115053.jpg
    133.9 KB · Views: 83
  • 20181007_115905.jpg
    20181007_115905.jpg
    147.1 KB · Views: 86
To avoid these ads, REGISTER NOW!

Bert_

Well-known member
Joined
Dec 24, 2016
Messages
9,931
Location
NW Iowa
Re-do the outside conduit so it comes into the back of the panel.

Or put a pull box in the wall below the panel but you cannot bury it in the wall the cover must remain accessible once the wall is done.

*edit, I see you are going to use SE cable which is fine without conduit for any part of the run. After the LB just run it in the wall and use a clamp to enter the panel. Make sure you are using the appropriate 4 wire cable which is normally referred to as SER rather than just SE.
 
Last edited:

Aceman

Well-known member
Joined
Jan 28, 2007
Messages
2,513
Location
Eastern Oregon
If it was mine, I would completely remove the exterior conduit as you have it.

I would sheet/weatherproof the exterior of the garage first.

Then I would install a short straight conduit sleeve from the right side of the meter main directly into the wall cavity with an end bell on it. SE cable would chase through this sleeve and through the garage wall framing horizontally and up and into the panel.

This will be cleaner and simpler than the setup you're trying to go with. Be sure to duct seal the conduit to keep cold/warm air from mixing.
 
OP
D

Dansz24

Member
Joined
Oct 7, 2018
Messages
7
Location
Mobile al
Then I would install a short straight conduit sleeve from the right side of the meter main directly into the wall cavity with an end bell on it. SE cable would chase through this sleeve and through the garage wall framing horizontally and up and into the panel.

That would be easier but I can't move the sub panel to be directly next to the main panel. This garage is an addition and there isn't a full bay to install the panel there.

I asked the builder about siding and he wants the electrical inspected before the exterior is put up, not sure why.
 

Aceman

Well-known member
Joined
Jan 28, 2007
Messages
2,513
Location
Eastern Oregon
That would be easier but I can't move the sub panel to be directly next to the main panel. This garage is an addition and there isn't a full bay to install the panel there.

I asked the builder about siding and he wants the electrical inspected before the exterior is put up, not sure why.

I think you're misunderstanding my post.

The conduit out of the metermain would just be a sleeve into the garage wall framing. It wouldn't run complete to the subpanel.

This would allow you to run SE into the garage framing and over to where ever the subpanel is located.
 
To avoid these ads, REGISTER NOW!
OP
D

Dansz24

Member
Joined
Oct 7, 2018
Messages
7
Location
Mobile al
I think you're misunderstanding my post.

The conduit out of the metermain would just be a sleeve into the garage wall framing. It wouldn't run complete to the subpanel.

This would allow you to run SE into the garage framing and over to where ever the subpanel is located.
Ahh. I'm tracking now! So SER is OK to run un-protected inside the wall cavity. I plan to drywall the garage in the future.
 

Bert_

Well-known member
Joined
Dec 24, 2016
Messages
9,931
Location
NW Iowa
Ahh. I'm tracking now! So SER is OK to run un-protected inside the wall cavity. I plan to drywall the garage in the future.

The rules for it are similar to romex except you can also run it outside. I like to sleeve it outside like Aceman is suggesting because the plastic jacket gets brittle after years in the sun.

Looks like you got the correct 4 wire stuff.
 
OP
D

Dansz24

Member
Joined
Oct 7, 2018
Messages
7
Location
Mobile al
Great, thank you for all the help.

Next question, I know the ground and neutral need to be isolated at the sub panel. Where does the ground and the neutral in the sub panel get connected at the main panel? I assume the neutral gets connected where all the other neutrals are but does the ground go there as well?
 

wyliesdiesels

Well-known member
Joined
Aug 14, 2012
Messages
20,279
Location
Modesto, CA
Great, thank you for all the help.

Next question, I know the ground and neutral need to be isolated at the sub panel. Where does the ground and the neutral in the sub panel get connected at the main panel? I assume the neutral gets connected where all the other neutrals are but does the ground go there as well?

If its truly the main service panel, then all grounds and neutrals can terminate on the neutral bar since it is bonded.

The main service panel is the only panel where this can occur...

refer to comment #3 on here:

https://www.garagejournal.com/forum/showthread.php?t=356460
 
OP
D

Dansz24

Member
Joined
Oct 7, 2018
Messages
7
Location
Mobile al
I have 2 dedicated outlets in the ceiling in my garage for garage door openers. Do these outlets need to be gfci or afci protected?
 