In floor heat and control cuts

Ord

Well-known member
Joined
Nov 3, 2009
Messages
93
Location
Ontario, Canada
I am about to lay out the pex, and I was wondering what you all do about the crack control cuts. It will make a very complicated layout if I try to keep the tubing from running under all the lines that will be cut.

The pex is being tied to wire mesh, so it will get pulled up to (hopefully) just about half way when the floor is poured, but I do worry that it might end up too high somewhere.
 
To avoid these ads, REGISTER NOW!

Possum

Well-known member
Joined
Dec 10, 2008
Messages
302
Location
KS
Since it will be hard to say where that pex and mesh will end up (my bet is the bottom) maybe a tooled joint or zip strips could be the hot ticket.
 
OP
O

Ord

Well-known member
Joined
Nov 3, 2009
Messages
93
Location
Ontario, Canada
I wonder if I am better off just leaving the mesh and pex at the bottom and adding some rebar higher up?
 

pstnbly

Well-known member
Joined
Jul 20, 2010
Messages
766
Location
So. Vermont
The pex should be sleeved in pvc conduit at the control joint ( .5 inch pex .75 inch conduit about 6inches either side of the joint)
 
To avoid these ads, REGISTER NOW!
OP
O

Ord

Well-known member
Joined
Nov 3, 2009
Messages
93
Location
Ontario, Canada
The sub contractor who will do the concrete is coming later today, I'll discuss options with him. We are planning to pour on Friday. The mesh and pex are already laid out and tied.

I know that the builder I am using normally uses just wire mesh and they don't do any cuts at all.
 

custom1

Well-known member
Joined
Jan 8, 2008
Messages
307
Location
Pa
What are the dimensions? The garage we built at my last house (1988) was 24x24x5". It didn't have any control joints and it never cracked anywhere. It even had an apron 2 feet outside the doors that people said would break off, but it never did.


My new garage floor is about 27x35 with pex tied to the mesh and pulled up(probably on the bottom) and I used the zip strips. I had never seen them before. I like the way it came out. You can just barely tell where they are and there is no groove in the floor to fill up with crud. I don't have any sleeves at the few places the pex crosses the joints. I figured if the floor moves enough to break the pex I have big problems.

John
 

nate379

Banned
Joined
Feb 2, 2009
Messages
7,279
Location
Palmer, AK
Nothing at my place. Just pex and the cuts. If the slab moves enough to tear open the Pex you have other issues to worry about as well IMO.
 
OP
O

Ord

Well-known member
Joined
Nov 3, 2009
Messages
93
Location
Ontario, Canada
What are the dimensions? The garage we built at my last house (1988) was 24x24x5". It didn't have any control joints and it never cracked anywhere. It even had an apron 2 feet outside the doors that people said would break off, but it never did.

John

The dimensions are 26'x40'x5.5"

I'll ask about those strips.
 

stingry

Well-known member
Joined
Oct 14, 2006
Messages
736
Location
Western Nebraska
I just poured my 3700 sq ft floor. Layed down 2" insulation board, stapled the pex to it then laid wire mesh over the pex. 5" of concrete. This way I know where the pex is (at the bottom) and can cut control joints wherever necessary. Most people think that the mesh and rebar should be near the center of the pour but this is incorrect. Concrete has little resistance to tension but is excellent in compression. When a vertical load is placed on a slab, the compression load is at the top of the slab and the tensile load is at the bottom, thus the need for mesh/rebar near the bottom.

Cheers:beer: