are you using OSB or plywood?
looks like you are 24" on center, you will need the clips between the sheets, centered between the trusses, be sure to span at least 3 trusses with a sheet (4')
I use a 1/2 crown stapler with a 2" staple, have an antique DuoFast stapler that is contact fire, hold the trigger and bump to actuate, you can nail a sheet as fast as you can walk
and I guess you know you start at the bottom (soffit) just like most things
and some young athletic, weight-lifting guys that want to show their stamina to buck the sheets to the roof, always fun to see the 200 lb bench press guys wilt after about 50 or so sheets
just make sure everything is square and the first sheet is aligned square, leave the recommended gaps at the ends, a nail is a good gage, the clips will maintain the gap between the long edges
goes on pretty quick, up the roof 4 feet at a time