Got the sheetrock done & painted, the epoxy floor is done, the spiral stair installed, and the 2-post set inside the building. No, it hasn't been bolted down yet so thats why its "wider" than one would expect.
I placed some of my toys inside after the floor cured to get them out of other storage spaces...
Next on the list, get the 39 running good so I can move it in and out, install the lift properly, install my jib, corrugated tin around the perimeter of the large bay, install three interior doors, finish the loft where the hot tub is temporarily sitting (one more interior window), install VCT on the hot tub room floor, trim out windows and doors... and of course the finish electrical with its inspection.
Will this beast ever be done???? LOL
Hope everyone is well!