In a major house remodel, added a 240 plug in the laundry for an electric dryer. Ran a single 10/3 through a new conduit out the top of the breaker box through the eve.
A sub contracted electrician later ran some new circuits and ran 2 - 12/2 wires through some poorly installed flex into the bottom of the breaker box less than 2' from the nearly empty new conduit that they were told to run through. They actually made more work for themselves. They really botched the hole through the eve, and the flex looks terrible. Photo attached.
Were they lazy, was there a reason they did this, and is the flex to code? If they were just being lazy, is it reasonable to make them fix this?
Thanks for any input.
Sent from my Pixel XL using Tapatalk
A sub contracted electrician later ran some new circuits and ran 2 - 12/2 wires through some poorly installed flex into the bottom of the breaker box less than 2' from the nearly empty new conduit that they were told to run through. They actually made more work for themselves. They really botched the hole through the eve, and the flex looks terrible. Photo attached.
Were they lazy, was there a reason they did this, and is the flex to code? If they were just being lazy, is it reasonable to make them fix this?
Thanks for any input.