Just to vent a bit and echo some of the above since I had a bad experience.
1. No way to know what is adequate or not without a soil test and engineer. No way. It may be well intentioned but it is all internet speculation. Don’t make this mistake.
2. The framing, plastic beams, rebar, and rebar supports all need to be 100% before you allow concrete. My guy said he would put put in supports and fix a framing issue, then just poured and walked away. Nothing, nothing you can do at that point to fix the pour. And if you don’t pay him, things can get ugly in the concrete world.
3. Triple check square and level before the pour. Get a pro to do it if needed. Laser levels, transoms, etc.
4. Extra thickness and rebar at the likely lift location costs almost nothing. Throw it on top of the rebar grid and tie in. The real expense will be the soil test, engineer, and materials they specify. And increasing the specs by a bit if you choose. Take pics before you pour….seriously, it all looks different after.
5. Get a friend or hire someone whose only job is to check in the concrete trucks and look the drivers in the eye and say “no added water.” Make them say they understand. Then your job is to turn off the water to the site until the pour is complete and watch the chute on every truck until they are done. Turn your back for a second and they add 30 gallons.
Hope it works out. First concrete job is a real learning experience. Unfortunately.
All the best.