In My Garage
Well-known member
My MaxJax came supplied with Wej-It PD-58 Power Drop anchors.
The reason for this post is due to my curiosity more than anything else, since I've gone with a totally different installation system for my MaxJax.
Looking at Dannmar's Instruction Manual as well as that from Wej-It, things didn't add up and performing a search didn't come up with anything.
The FAQs on Dannmar's site regarding the MaxJax calls for a minimum 4 inch concrete thickness...from their site:
Then in the MaxJax Instruction Manual, they state the following:
The above pic clearly shows solid concrete to beyond the end of the carbide drill bit.
From the Wej-It site, the PD-58 anchors call for a minimum 5 inch hole depth:
The question now is, does it matter if the anchors protrude "through" the concrete slab which would be the case based on the minimum required floor thickness, or do they have to be set into a "blind hole" which would mean a thicker floor requirement. And if they need to be in a "blind hole" as Fig 11 depicts, how much concrete, if any, is required beyond the end of the hole?
The reason for this post is due to my curiosity more than anything else, since I've gone with a totally different installation system for my MaxJax.
Looking at Dannmar's Instruction Manual as well as that from Wej-It, things didn't add up and performing a search didn't come up with anything.
The FAQs on Dannmar's site regarding the MaxJax calls for a minimum 4 inch concrete thickness...from their site:
Then in the MaxJax Instruction Manual, they state the following:
The above pic clearly shows solid concrete to beyond the end of the carbide drill bit.
From the Wej-It site, the PD-58 anchors call for a minimum 5 inch hole depth:
The question now is, does it matter if the anchors protrude "through" the concrete slab which would be the case based on the minimum required floor thickness, or do they have to be set into a "blind hole" which would mean a thicker floor requirement. And if they need to be in a "blind hole" as Fig 11 depicts, how much concrete, if any, is required beyond the end of the hole?
Last edited: