cdnc
Well-known member
A quick video tour of finished product (Sept 2020)
We have finally started the build for a small 30x40 equipment storage / shop / barn build on our farm. Friends locally have used a great Mennonite builder to put up similar structures and to repair bank barns. The only challenge is that he is really busy
We finalized the plans in the summer and obtained the permit in September. Removed a hoop house that was on site (and historically the site of a farm building that was removed in the 1970s). We've been waiting for the concrete crew to be available given other projects. Finally had the go for late December.
Local excavator cleared the land and dug the foundation last week for the footings and foundation wall. Concrete crew (2 guys) came last week and poured footing then poured the rataining walls. We started back filling this week
Started with some gravel and then filled with limestone screening with me and my two boys packing each lift. Hope to start framing work soon and should be finished in 3 - 4 days. We are going to wait for everything to settle and will then insulate and pour slab. Plan to install pex for radiant floor heat to have option in the future.
Building is 30x40x12, two story traditionally framed building. There are three 10x10 rollup doors, an oversized man door (36"x92") a horizontal window on first floor, two windows on second floor and six skylights. There is a single post on main floor to support steel beam.
We have finally started the build for a small 30x40 equipment storage / shop / barn build on our farm. Friends locally have used a great Mennonite builder to put up similar structures and to repair bank barns. The only challenge is that he is really busy
We finalized the plans in the summer and obtained the permit in September. Removed a hoop house that was on site (and historically the site of a farm building that was removed in the 1970s). We've been waiting for the concrete crew to be available given other projects. Finally had the go for late December.
Local excavator cleared the land and dug the foundation last week for the footings and foundation wall. Concrete crew (2 guys) came last week and poured footing then poured the rataining walls. We started back filling this week
Started with some gravel and then filled with limestone screening with me and my two boys packing each lift. Hope to start framing work soon and should be finished in 3 - 4 days. We are going to wait for everything to settle and will then insulate and pour slab. Plan to install pex for radiant floor heat to have option in the future.
Building is 30x40x12, two story traditionally framed building. There are three 10x10 rollup doors, an oversized man door (36"x92") a horizontal window on first floor, two windows on second floor and six skylights. There is a single post on main floor to support steel beam.
Attachments
Last edited:
