Mesh on pex in concrete question

MScott

Well-known member
Joined
Jun 30, 2009
Messages
1,616
Location
Eastern Ontario
I just finished laying out the pex for my garage floor and have stapled it down on top of the foam and placed the mesh on the pex. My question is whether I need to tie the mesh down to the pex is it ok just laying there.
 
Last edited:
To avoid these ads, REGISTER NOW!

gatchel

Well-known member
Joined
Dec 12, 2009
Messages
672
Location
West of King of Prussia, PA
I just finished laying out the pex for my garage floor and have stapled it down on top of the foam and placed the mesh on the pex. My question is whether I need to tie the mesh down to the pex is it ok just laying there.



Typically the mesh is not at the bottom of the slab. Some people say the middle, some people say the bottom third of the pour.
 
Last edited:

stingry

Well-known member
Joined
Oct 14, 2006
Messages
732
Location
Western Nebraska
I just finished laying out the pex for my garage floor and have stapled it down on top of the foam and placed the mesh on the pex. My question is whether I need to tie the mesh down to the pex is it ok just laying there.

It is fine just laying on top of the PEX. The weight of the concrete and the finishers walking on it will keep it in place.

Cheers
Steve
 
OP
M

MScott

Well-known member
Joined
Jun 30, 2009
Messages
1,616
Location
Eastern Ontario
Typically the mesh is not at the bottom of the slab. Some people say the middle, some people say the bottom third of the pour.

The mesh will not actually be at the bottom of the slab (which would make it completely useless,) it will be on top of the pex which places it in the bottom third of the slab. I have searched this and the consensus seems to be that placing it on top of the pex is the best compromise. I considered suspending the mesh on stands, but I know that when the workers walk on it during the pour it just gets pushed down anyway and counting on them to lift it up is not likely to happen. I just have not seen anyone mention whether the mesh should be tied down or not.
 

Highbeam

Well-known member
Joined
Feb 15, 2011
Messages
2,292
Location
Mt Rainier foothills, WA
It won't float up. So long as the concrete guys don't trip on it and lift it somehow screw up by blasting concrete under it, the mesh will stay down. Use the big flat sheets that lay nice and flat and tie them together at the edges to minimize the chance of the above accidents.
 
OP
M

MScott

Well-known member
Joined
Jun 30, 2009
Messages
1,616
Location
Eastern Ontario
Thanks. I couldn't see any reason it would have to be tied down, but it isn't something that can be changed after the pour. I appreciate the thoughts.
 
To avoid these ads, REGISTER NOW!

maxspeed96ct

Well-known member
Joined
Apr 6, 2012
Messages
379
The mesh is fine on top of the tubing . I've heard debates before reguarding the mesh being in contact with the tubing causing issues if there's expansion and contraction, but working in the industry we always have done it this way and haven't had any issues. Personally I think the tubing movement is so minimal and the tubing is pretty rugged .
 

maxspeed96ct

Well-known member
Joined
Apr 6, 2012
Messages
379
Where would the tubing go?......it is encased in concrete! Or amI missing something?

That's what I said , but some of these engineers fresh out of college just like to pretend they really know what they are doing ..
 

jloram

New member
Joined
Jun 16, 2013
Messages
3
A couple of things to consider: If the PEX is under the mesh it's going to difficult to make repairs if the concrete guys rupture a tube. I tied my PEX to the re-bar in my six inch slab, pressurized the tubing and then stood by when the slab was poured to make fixes. (You'll know instantly if they bust a tube!) (see http://www.loram.org/Mt House Shop Construction.htm)
 

powerhound

Well-known member
Joined
Apr 23, 2012
Messages
89
Where would the tubing go?......it is encased in concrete! Or amI missing something?

I was told that the pex tends to "float" because of how it comes coiled. For that reason, I put mesh (suspended 1" off of the foam board) zip tyed my pex to the top of that and then put rebar on top of that so that when I saw cut my slab, I would have the rebar as a warning "barrier" if I got to close to the tubing.
 

Highbeam

Well-known member
Joined
Feb 15, 2011
Messages
2,292
Location
Mt Rainier foothills, WA
The mesh can be cut in a flash with a cutting tool like snips or bolt cutters depending on gauge. Depending on your method of repair, you can easily work through the 6" grid.
 