WI/MI Border
Well-known member
- Joined
- Jan 27, 2025
- Messages
- 196
A friend helped me lift and secure 13 trusses and the gable (drop) trusses. 24" OC, 24' long, 6/12 pitch.
The bottom cord is straight and true (24" oc) along all 13 regular trusses. I checked for plumb on all 13 and though I used steel truss braces for spacing (two rows about 4' from the peak) the peak is out of plumb as much as 1" (see below). Fortunately they all lean slightly to the west. Contributing to this, I think, is the steel bracing. It could be that the steel bracing was installed incorrectly as some of the "teeth" didn't imbed into the truss as much as it should have. Though I think warping of the trusses are the main culprit.
My gable ends are plumb. They are braced from the highest point of the gable web to the bottom cord of the truss two trusses in. Starting on the west end the next 13 trusses are approximately the following amount out of plumb at the peak, mostly leaning west except for three which are plumb. This was an "eyeball" estimate but close.
1/4", 1/2", 3/4", plumb, plumb, 1/2", plumb, 3/4", 1/4", 1/2", 1/2", 1", 1"
My friend suggested that I pull all 13 trusses as one unit with a strap. I'm not sure if I want to approach a fix this way since they vary in distance out of plumb. I'm curious if there is a better method. The height of the truss from bottom to top cord is just over 6' so a 1/4" in six feet is not too bad but with almost all of them leaning west I thought it was a good idea to correct as much as I can.
I have yet to measure the total peak distance from gable to gable. However, if that result comes out to 28' (design) would cutting/installing individual bracing at or near the peak between trusses be advisable? Or would you suggest bracing the peak with long 2x4s premeasured for 24" OC spacing and attached under the top cord?
Thanks for the advice, Tim
The bottom cord is straight and true (24" oc) along all 13 regular trusses. I checked for plumb on all 13 and though I used steel truss braces for spacing (two rows about 4' from the peak) the peak is out of plumb as much as 1" (see below). Fortunately they all lean slightly to the west. Contributing to this, I think, is the steel bracing. It could be that the steel bracing was installed incorrectly as some of the "teeth" didn't imbed into the truss as much as it should have. Though I think warping of the trusses are the main culprit.
My gable ends are plumb. They are braced from the highest point of the gable web to the bottom cord of the truss two trusses in. Starting on the west end the next 13 trusses are approximately the following amount out of plumb at the peak, mostly leaning west except for three which are plumb. This was an "eyeball" estimate but close.
1/4", 1/2", 3/4", plumb, plumb, 1/2", plumb, 3/4", 1/4", 1/2", 1/2", 1", 1"
My friend suggested that I pull all 13 trusses as one unit with a strap. I'm not sure if I want to approach a fix this way since they vary in distance out of plumb. I'm curious if there is a better method. The height of the truss from bottom to top cord is just over 6' so a 1/4" in six feet is not too bad but with almost all of them leaning west I thought it was a good idea to correct as much as I can.
I have yet to measure the total peak distance from gable to gable. However, if that result comes out to 28' (design) would cutting/installing individual bracing at or near the peak between trusses be advisable? Or would you suggest bracing the peak with long 2x4s premeasured for 24" OC spacing and attached under the top cord?
Thanks for the advice, Tim

