EdT
Well-known member
I recently installed a pair of mini-splits in my new two story shop building. My power company provides an incentive for allowing them to install load managers on AC systems so they can better manage the peak loads during the summer. They were not able to do so on the mini-splits because, unlike a "conventional" system, the control circuit runs at line voltage and the load manager is set up to interupt the "normal" low voltage control signal to the contactor for the compressor. Anyone have a solution for this problem?