Hi All,
I am getting ready to build a 30'x30' Garage with what will eventually be an apartment upstairs... basically a 2 story building-all block.
It will be sitting at a very low spot, on a very low lot in Florida- and will require at least 2 1/2' of fill. I have had the soil tests, and we do not need pilings.
The engineer that drew the plans, provided a site plan showing stem wall construction, but construction details show a monolithic slab. (The main house is stem wall)
Now that I am putting it out to bid, I am getting lots of questions from the contractors as to which way I want to go..
It seems that Stem Wall would disturb the site less and require less fill, but I've heard it is considerably more expensive... is it?
One other thing I would be interested in some comments.. I asked 2 shell contractors for a number for just the slab and block (Monolithic Slab and 2 stories of block) and they came in between $30 and 40K.. I was thinking I'd be at least a third of the cost there, but the numbers I'm getting from contractors are about $185,000..really? We are talking just a GARAGE... are they just really greedy, or on crack?
I am getting ready to build a 30'x30' Garage with what will eventually be an apartment upstairs... basically a 2 story building-all block.
It will be sitting at a very low spot, on a very low lot in Florida- and will require at least 2 1/2' of fill. I have had the soil tests, and we do not need pilings.
The engineer that drew the plans, provided a site plan showing stem wall construction, but construction details show a monolithic slab. (The main house is stem wall)
Now that I am putting it out to bid, I am getting lots of questions from the contractors as to which way I want to go..
It seems that Stem Wall would disturb the site less and require less fill, but I've heard it is considerably more expensive... is it?
One other thing I would be interested in some comments.. I asked 2 shell contractors for a number for just the slab and block (Monolithic Slab and 2 stories of block) and they came in between $30 and 40K.. I was thinking I'd be at least a third of the cost there, but the numbers I'm getting from contractors are about $185,000..really? We are talking just a GARAGE... are they just really greedy, or on crack?