I have just moved to a different home and the shop was added onto in 2003. The original structure is a 20x28 floating slab with stem walls for the structure to set on.
They added a 4x28 section in the back and it is monolithic. It has sank about 1 and 1/2 inches in a back corner which has left a large gap nearly the whole 28' length.
I had a well known company give me an estimate of 7K for poly jacking. I have a mud jacking company coming out in a few days to give an estimate.
7K seems a bit excessive, and their recommended repair was piers at 27K
Which method is better?