Good morning,
Question about doing multiple pulls thru the same conduit. I'm going from the panel thru 1-1/2" PVC that I placed under the slab across the shop before poured. It is about a 55' run has 3 90* sweeps to a junction box. 2 -220/50a and 2-110/20a (4 #6, 2#10 and 6#12). If I only pull half, one 220 and one 110 circuit with an extra mule tape how tough will it be to pull the other circuits later? Total conduit fill would be under 20%.
Question about doing multiple pulls thru the same conduit. I'm going from the panel thru 1-1/2" PVC that I placed under the slab across the shop before poured. It is about a 55' run has 3 90* sweeps to a junction box. 2 -220/50a and 2-110/20a (4 #6, 2#10 and 6#12). If I only pull half, one 220 and one 110 circuit with an extra mule tape how tough will it be to pull the other circuits later? Total conduit fill would be under 20%.