PartsGuy27
Well-known member
Hello everyone!
After 6 years of owning my home, I have started to build my dream garage.
I had the backyard graded where an above ground pool used to be, removed 2 trees and had shale brought in for a base for the building.
I went with a 30'X32' pole building from Pioneer Pole Buildings. I had originally planned to go 30' X 40' but the township makes it very difficult to build a garage over 1000 sq/ft. So 30'X32' (960 sq/ft) it is.
The building has 2 10' X 10' garage doors installed. The concrete was poured at 5" thick. Before the concrete was poured, I put in a 4" and a 2" piece of conduit so i can run electric and water.
I had an existing sidewalk from my patio out to where the pool used to be. I asked that the man door to the garage be lined up to the sidewalk. They were about 18" off center and I am currently fighting with them to widen the sidewalk to make it line up with the door.
I am now tasked with installing the electrical and water lines followed by insulation and drywall before I coat and finish the floor.
I have purchased 18, 4' LED shop lights. Can never have too much light!
I am hoping to have this done by fall, all advice is appreciated.
Thank you!
After 6 years of owning my home, I have started to build my dream garage.
I had the backyard graded where an above ground pool used to be, removed 2 trees and had shale brought in for a base for the building.
I went with a 30'X32' pole building from Pioneer Pole Buildings. I had originally planned to go 30' X 40' but the township makes it very difficult to build a garage over 1000 sq/ft. So 30'X32' (960 sq/ft) it is.
The building has 2 10' X 10' garage doors installed. The concrete was poured at 5" thick. Before the concrete was poured, I put in a 4" and a 2" piece of conduit so i can run electric and water.
I had an existing sidewalk from my patio out to where the pool used to be. I asked that the man door to the garage be lined up to the sidewalk. They were about 18" off center and I am currently fighting with them to widen the sidewalk to make it line up with the door.
I am now tasked with installing the electrical and water lines followed by insulation and drywall before I coat and finish the floor.
I have purchased 18, 4' LED shop lights. Can never have too much light!
I am hoping to have this done by fall, all advice is appreciated.
Thank you!