Figured I start my own thread to share with everyone here. Few weeks back got the permit to build. My brother offered to do the site prep for cheap. :thumbup: He came over on 5/9 for only a few hrs to dig some stumps as he got a call for another job. :( I'm hoping he can come this weekend!
 
To avoid these ads, REGISTER NOW!
OP
Z

zrxrider

Well-known member
Joined
Dec 25, 2008
Messages
87
Location
NJ
Ok, ok, guys........Here is my bro taking out a stump. I called him yesterday and he's coming over Sat. to do more prep. work. :beer::thumbup::bowdown:

001.jpg
 
OP
Z

zrxrider

Well-known member
Joined
Dec 25, 2008
Messages
87
Location
NJ
Well, he dropped the backhoe off today and said he'll be here 8am. :beer: I'll be sure to take pics for ya'll.
 
OP
Z

zrxrider

Well-known member
Joined
Dec 25, 2008
Messages
87
Location
NJ
Really? I see the pic.....

He got alot done and is coming tomorrow too. Pics coming after my sons baseball game......
 
OP
Z

zrxrider

Well-known member
Joined
Dec 25, 2008
Messages
87
Location
NJ
Its been awhile........my brothers boss was looking for free shale for a solid base and had 10 tri axle loads put in! Almost ready for the guys from Shirk to come and put up the building. :rocker: I'll post pics asap.
 
OP
Z

zrxrider

Well-known member
Joined
Dec 25, 2008
Messages
87
Location
NJ
Things are moving now! Monday the trusses etc. were delivered. My dog "TURBO" is inspecting too! hehehehe

8.jpg



Tuesday they dug the holes and I helped mix cement for the footings. Good thing I had 2 wheel barrows laying around! The code guy wanted a wet pour and wouldn't accept just tossing bags in the hole.

Today(Thur.), they came to set the poles etc. Man, they go up FAST and make it look so easy.

10.jpg


13.jpg


14.jpg


15.jpg


And heres the last as it started to rain and went home. Was hoping to see them finish Friday but inspection for the purlins wasn't planned so they'll be back Monday. Heres the last pic when they left today.....

16.jpg
 

Re-Volv

Well-known member
Joined
Mar 11, 2008
Messages
77
Lookin good! They sure do go up fast!

If you don't mind me asking, what's the building going to run you?
 
OP
Z

zrxrider

Well-known member
Joined
Dec 25, 2008
Messages
87
Location
NJ
Thanks! It will be SOOOO nice to have a place to play in out of the weather and have all my things organized for once.
 
OP
Z

zrxrider

Well-known member
Joined
Dec 25, 2008
Messages
87
Location
NJ
The inspection was a joke. Guy came out, looked up under the overhead door area and passed it. LOL
 
To avoid these ads, REGISTER NOW!

jumbo61

Well-known member
Joined
Sep 9, 2008
Messages
78
Location
Dysfunctional, NY
Very nice. Do you have any complaints with Shirk? I'm looking at doing a similar building. Would you mind giving the package price? Did you insulate the roof? One last question. Do you know the height to the peak? Thanks.
 
OP
Z

zrxrider

Well-known member
Joined
Dec 25, 2008
Messages
87
Location
NJ
No complaints. Leon, is a great salesman! He was NEVER pushy or anoyed by my millon questions or changes. The crew busted their butts and did a great job building my dream garage!!
 

yellow2000S/R

Member
Joined
Jul 4, 2009
Messages
23
Looks nice!

Are you framing in the bottom and getting concrete poored? Insulation and wiring going up? What are you going to do for the interior finishing?
 
OP
Z

zrxrider

Well-known member
Joined
Dec 25, 2008
Messages
87
Location
NJ
Thanks.....

For now, I'm just putting stone down inside and need to add fill on the outside and pitch it away from the building. I do want to add wiring and insulation but need to save my pennies. LOL I'm just happy it finally up!

Heres a shot of the inside:

008.jpg
 
Last edited:

LenS

Member
Joined
Apr 3, 2009
Messages
24
Location
Teaneck, NJ
Hi Mike,

Thanks for posting these and for chatting with me about your Shirk experience. I've now spoken to three satisfied Shirk customers, which always eases the decision process.

Hope to see my garage up in the near future.

Len
 
OP
Z

zrxrider

Well-known member
Joined
Dec 25, 2008
Messages
87
Location
NJ
Yup, what krooser said....... Still need to pour a floor after I find some $$.
 
OP
Z

zrxrider

Well-known member
Joined
Dec 25, 2008
Messages
87
Location
NJ
Well, FINALLY got the floor poured. I'm happy its done after 2 years but got cracks after 1 week! :mad::mad::mad:
 
OP
Z

zrxrider

Well-known member
Joined
Dec 25, 2008
Messages
87
Location
NJ
I am looking a Shirk right now do you have any complaints after two years, and who did you have do the concrete.

Shirk did the floor too. I just noticed ANOTHER crack in the approach......no major issues with the building so far.

whats the roof pitch??

The pitch is 4/12

I guess its about time to add new pics, huh?
 
OP
Z

zrxrider

Well-known member
Joined
Dec 25, 2008
Messages
87
Location
NJ
Well here is one of the cracks..........:mad::mad::mad:
 

Attachments

  • 042.jpg
    042.jpg
    79.1 KB · Views: 60