Long story short, I had a contractor (actual friend of mine) lined up to install the poles for my 26x40 building and after he had a scheduled date for me he kept pushing me off. After 2 weeks of him pushing me off he finally said he didn't have time in his schedule to do it anymore (some friend.....). So I figured I would just handle it all and save some money.
Now I need help with building inspections. What need inspections for a pole building and how long in advanced do you typically schedule in inspection for?
Only reason I ask because today is Veterans day and building department is closed right now.