Hi folks,
We are just finishing up a pad for a 40x48x14 pole barn. Total size is about 50 x 60. The area where the barn is going is on a slight grade so one end of the pad needed about 2.5' of fill and the other end needed almost nothing. No money to deal with a retaining wall on the fill side so we plan to taper the pad off 3:12 to 4:12 and sod or lay straw or something. All the doors are on the side of the pad that needed minimal fill.
The barn will have laminated posts (6' of which is PT) and set on cookies.
I live in an area of NC where the inspector isn't very familiar with lam posts, cookies, radiant flooring, etc. so he has a lot of questions and Im getting minimal advice from him.
Two questions here:
1. On the side of the pad with 2.5' fill, I have concerns about getting the footing down into virgin dirt enough. The builder typically augers 4' in the ground, sets cookie and post on that which means the post will only be in virgin soil best case 4' - 2.5' - 6" (cookie) = 1 foot. We have option to get longer posts or auger deeper and pour a footer? We cant just set the standard posts deeper because there needs to be 2' of PT above grade.
2. Because the property is on a grade (~2.5%), I want to elevate the front of the building so I'm not driving down into it. My plan is to have them set the skirt so finished grade (concrete floor) is ~12" above the pad. This will likely result in me coming back after barn is up to add a second skirt below the first, put some tin over the skirts to keep water away and blending some #57 up to the base.
Any thoughts here? I can get posts 2' longer on PT side for ~20$ more each.
thanks!!
Drew
We are just finishing up a pad for a 40x48x14 pole barn. Total size is about 50 x 60. The area where the barn is going is on a slight grade so one end of the pad needed about 2.5' of fill and the other end needed almost nothing. No money to deal with a retaining wall on the fill side so we plan to taper the pad off 3:12 to 4:12 and sod or lay straw or something. All the doors are on the side of the pad that needed minimal fill.
The barn will have laminated posts (6' of which is PT) and set on cookies.
I live in an area of NC where the inspector isn't very familiar with lam posts, cookies, radiant flooring, etc. so he has a lot of questions and Im getting minimal advice from him.
Two questions here:
1. On the side of the pad with 2.5' fill, I have concerns about getting the footing down into virgin dirt enough. The builder typically augers 4' in the ground, sets cookie and post on that which means the post will only be in virgin soil best case 4' - 2.5' - 6" (cookie) = 1 foot. We have option to get longer posts or auger deeper and pour a footer? We cant just set the standard posts deeper because there needs to be 2' of PT above grade.
2. Because the property is on a grade (~2.5%), I want to elevate the front of the building so I'm not driving down into it. My plan is to have them set the skirt so finished grade (concrete floor) is ~12" above the pad. This will likely result in me coming back after barn is up to add a second skirt below the first, put some tin over the skirts to keep water away and blending some #57 up to the base.
Any thoughts here? I can get posts 2' longer on PT side for ~20$ more each.
thanks!!
Drew