Hi i am struggling to get answers , as i need a quick one !!! can you help , i am currently coating my garage floor with International 275 hs which is a solvent based two pack epoxy .
i have plenty of extra paint left over after my first two coats and was wanting to add a third .
this is what i have done so far :
1st coat 4:1 ratio mix with 10% thinners
2nd coat is straight 4:1 mix- 24hrs after 1st coat
3rd ?????? can i add a 3rd 4:1 - 24hrs
Thanks Heap
i have plenty of extra paint left over after my first two coats and was wanting to add a third .
this is what i have done so far :
1st coat 4:1 ratio mix with 10% thinners
2nd coat is straight 4:1 mix- 24hrs after 1st coat
3rd ?????? can i add a 3rd 4:1 - 24hrs
Thanks Heap