The bracing requirements are listed directly on the spec sheet...just below the table and to the right end......
I think one thing I left out that is probably important is this is going on a pole structure. So the back common Truss has two poles that go all the way up to the top chord at 10 foot intervals. The front common Truss will end up having 4 poles that go all the way up to the top Chord as well.
I saw where it recommended for the scissor trusses to be braced every 2 ft 2 inch on Center. But if I'm going to finish the inside do you guys think it would be best if I just put some sheathing for ceiling?
And unfortunately the truss company didn't give any additional information with the trusses might be worth a phone call on Monday