spschroeder
Active member
Hi all,
I'm upgrading from 100A overhead to 200A underground on an existing building.
The concrete slab the building is set on is wider than the width of the building by ~3.5 inches. That means my new 200A pedestal meter socket cannot sit flush to the building's exterior OSB sheathing because the pedestal needs to be buried 18" into the ground.
My options:
1) Rent a concrete saw and cut away the concrete to fit the 10" width of the pedestal and mount the pedestal flush to the building wall.
2) Frame out a 2x4 (3.5") "bump out" that matches the pedestal width and height dimensions; pedestal now sits away from wall and will need to get flashed, but I don't need to cut away concrete.
3) ...some other option I'm not thinking of but you might have!
What would you do?
Thanks in advance,
-Steve
I'm upgrading from 100A overhead to 200A underground on an existing building.
The concrete slab the building is set on is wider than the width of the building by ~3.5 inches. That means my new 200A pedestal meter socket cannot sit flush to the building's exterior OSB sheathing because the pedestal needs to be buried 18" into the ground.
My options:
1) Rent a concrete saw and cut away the concrete to fit the 10" width of the pedestal and mount the pedestal flush to the building wall.
2) Frame out a 2x4 (3.5") "bump out" that matches the pedestal width and height dimensions; pedestal now sits away from wall and will need to get flashed, but I don't need to cut away concrete.
3) ...some other option I'm not thinking of but you might have!
What would you do?
Thanks in advance,
-Steve
Last edited: